February 2003 Looking towards the future southbound tunnel at the north end of the University Station. |
February 5, 2003 Looking northwest from the
South side of the University of Alberta hospital. |

May
3, 2003
Fencing in place for TBM recovery hole. |

May
3, 2003
Walls at the SLRT site. |
 May 10, 2003 Looking south from 87 Ave into the SLRT site. |
 May 15, 2003 Mole
retrieval hole, installing piles. |
 May 20, 2003 Overhead view of the work taking place on the north side of the Education Car Park. |
 May 20, 2003 A view of the work to remove the piles where the TBM will have to start digging. |
 June 4, 2003 Looks like they are driving piles at the location of the mole
retrieval hole.
|
 June 4, 2003 Looking north into the portal work site. |
 June 4, 2003 Another shot looking north into the portal work site. |
 June 4, 2003 A form for a concrete box waiting for the concrete to be poured. This will be the location of the sump for the tunnels. |

June 23, 2003 Base slab construction looking south. |

June 23, 2003 Looking north towards the future portal. |

June/
July 2003
Base slab construction |

June/
July 2003
Mole hole construction. |

July 2003?
Base slab construction. |

July
2003?
Base slab construction. |

July
9, 2003
Looking north in SLRT site. |

July
9, 2003
Base slab construction. |
July
9, 2003
Looking north into SLRT site. |

July
2003
Forms to make spaces for laying track. |

July
2003
Base slab construction. |

July
2003
Base slab construction. |

July
14, 2003
TBM and base slab. |

August
2003
Start of work on retaining walls. |
 August 11, 2003 Retaining wall under construction.
|
 August 24, 2003 Retaining wall under construction. This view shows the
same panel as the previous photo, but in this pic the wall has been poured.
|
 August 24, 2003 A form for a wall ready to be poured.
|
 August 26, 2003 Retaining wall under construction. The wall is the same one in the previous photo, but here the concrete has been poured and is now draped in a cloth with water sprinkling onto it.
|

September
6, 2003
Looking south into SLRT site. |

September
11, 2003
Work on retaining walls. |

September
30, 2003
Looking north into the SLRT site at night. |

October 13,
2003
Looking northwest from the
South side of the University of Alberta hospital. |

October
26, 2003
Form for portal in place. |

October
26, 2003
Bottom of portal form. |

October
26, 2003
Dirt to fill in beside of retaining wall. |

October
28, 2003
Top of the forms for the portal. |

October
28, 2003
Forms for the portals. |

October
28, 2003
Forms for the portals. |

October
28, 2003
Cropped image showing the forms for casting the portals. |

November
30, 2003
Working to remove temporary tunnel liners. |

December
13, 2003
Looking north into SLRT site with the portals visible. |

December
13, 2003
Start of bored tunnel. |

December
18, 2003
Looking south along the east side of the retaining wall. |

January
14, 2004
Start of bored tunnel section . |

January
14, 2004
Entrance constructed inside of tunnel. |

April 26, 2004
Start of both bored tunnels. |

April 26, 2004
Wide angle shot of overall portal area. |

April 26, 2004
These look to be tunnel liners? that will be lowered in to complete the tunnel
through to University station. |

May
20, 2004
Work on SB cut and cover. |

May
20, 2004
Work on cut and cover frame for SB line. |

May
20, 2004
Working on cut and cover. |

May
20, 2004
Cut and cover at the start of the bored tunnel. 18mm lens. |

May
20, 2004
Cut and cover at the start of the bored tunnel. |

May
20, 2004
Cut and cover being tied in with the SB bored tunnel. |

May
20, 2004
Work on SB tunnel cut and cover section. |

May
20, 2004
Work on SB tunnel cut and cover section. 18mm lens. |

May
20, 2004
Cut and cover tied into the portal entrance. |

May
20, 2004
Cut and cover tied into the portal entrance.
18mm lens. |

May
20, 2004
Looking north.
18mm lens. |

May
20, 2004
Looking north towards bored tunnels. |

May
20, 2004
Looking north into worksite.
300mm lens. |

May
20, 2004
Looking north into worksite.
300mm lens. |

May
20, 2004
Cement trucks at the TBM recovery shaft helping with installation of the final
tunnel liners. |

May
20, 2004
Work on the surface for completing the last few tunnel liners. |

May
20, 2004
Looking south into northbound tunnel from University.
|

May
20, 2004
Looking south into northbound tunnel from University. |

May
20, 2004
Sign advertising replacement of trees removed so that the TBM could be
transported back to the launch wall. |
|