Construction of this section of the LRT system consisted of building 2 major overpasses for traffic, 2 bridges, and 2 Stations. Construction for the overpasses started as early as 1997 and completion by the year 2001 with LRT track work and station construction starting in the year 2000. The cost of this extension was $80.1-Million dollars (Not including the overpasses) and was completed by October 9th, 2001. The two LRT Stations that were constructed included the Canyon Meadows Station built off of MacLeod Trail at Canyon Meadows Drive and the Fish Creek/Lacombe Station which is located just off of MacLeod Trail at 146 Avenue. In this section, it will contain photos during the construction progress and the finished product broken up into groups of photos. Please click one of the photos below to view it's full size:
The view from Anderson Station overpass |
||||
April 14, 2001 |
May 13, 2001 |
May 20, 2001 |
June 4, 2001 |
June 12, 2001 |
June 14, 2001 |
June 22, 2001 |
August 14, 2001 |
August 21, 2001 |
Construction Timeline for the above photos:
Sorted by the date they were shot.
More photos of the construction and the end results will be added at a later time